The Challenge
A large networking hardware and software company wanted to move its engineering labs from on premises facility in Silicon Valley to a collocated data center in Washington state. The scope of the equipment to be moved included 25,000 servers and 3,000 cabinets.
Milestone Approach
Milestone designed a 12-phase project that would take 14 months. Milestone provided a turnkey solution that included project managers, logistics, engineering, and technician support.
Results
Milestone successfully planned and executed the 12 phases of the project in close collaboration with client stakeholders. We are able to minimize downtime and meet client expectations with positive CSAT.
By the Numbers
Metric | Value |
Servers relocated | 25,000 |
Cabinets relocated | 3,000 |
Project phases | 12 |
Project duration | 14 months |